Studemont/Heights Construction
March 25, 2011

IH 10 EASTBOUND AT STUDEMONT EXIT RAMP TO RE-OPEN THIS WEEKEND

“Motorists will now be able to access the newly constructed eastbound frontage road from Studemont to Taylor St.”

The IH 10 Eastbound Studemont exit ramp will re-open to traffic this weekend ahead of the projected construction schedule.  With the opening of the Studemont exit, motorists will now be able to access the newly constructed eastbound frontage road to Taylor St. Construction crews anticipate completing the final preparations to re-open the ramp by 10 p.m. Saturday, March 26, 2011.

Balfour Beatty Infrastructure earned the maximum incentive of $300,000 for completing the contract milestone and opening the ramp more than 30 days ahead of schedule.

Motorists should be advised that the next phase of work requires the closure of the IH 10 eastbound entrance ramp from Heights Blvd. which will be closed continuously from 7:00 a.m., Saturday, March 26 to 5:00 p.m., Sunday, July 31. Detour to the Taylor entrance.

Advertisements

Construction: Washington Ave. & Lockwood
March 10, 2011

LOCKWOOD: From IH  610 To CLINTON DRIVE
WASHINGTON AVE.: From WESTCOTT ST. To IH45/HOV
Construction Start: February 10, 2011
Construction Completion: July 10, 2011

Construction: Near Pearland
March 10, 2011

  • SH 35 from Clear Creek to FM 518 is still on going and progressing.  We are working on finishing the last bit of storm sewer construction between Orange Street south to FM 518.  We are starting paving work on the north end.  We are also working on bridge work at Town ditch and Hickory Slough also.
  • As for Cullen, we are very close to completely finishing the project.  The traffic is now in final configuration and we still have sidewalk, driveway and landscape to complete.
  • At Dixie Farm road from Clear Creek to SH 35, we are also very close to finishing the project.  Need to finish sidewalk and driveways and landscape,e tc.
  • Down south in Lake Jackson, we just switched traffic onto the newly built frontage road and start the milestone construction of the mainlanes and bridges. We will also be switching traffic on FM 2004 from BS 288 to This Way street.  After that we will have 3 more month’s work in storm sewer and asphalt overlay to complete the project.

Viewer Email:North Eldridge Construction
March 4, 2011

Jennifer:
 
Can you tell me WHO IS DOING OR NOT DOING THE PAVING, on North Eldridge at Emmett Road?
 
Somebody is going to have a wreck with all the uneven paving at this intersection.
 
Please help, your biggest fan!!
 
Bryan

A: Planned improvements on North Eldridge Parkway, between West Little York and FM 529, include installation of a continuous turn lane, appropriate drainage conveyance system, incorporation of dual northbound/southbound left turn lanes on North Eldridge Parkway at FM 529, traffic signal and fiber optic interconnect modifications.

The $2,525,703 project and construction activity commenced September 20, 2010.  Construction activity is scheduled for completion by May 17, 2011.